Karim takes 2 days longer than Rahim to produce x units of products. At these rates, Karim & Rahim together take 2 days to produce \(5/6^{th}\) of x units. How many days would Karim take to produce 3x units of this product?
A. 4 days
B. 6 days
C. 12 days
D. 18 days
Explanation: Let, Rahim takes y days to produce x units. So, in 1 day Rahim produces \(x/y\) units. So, Karim takes \(y+2\) days to produce x units. So, in 1 day Karim produces \(x/(y+2)\) units. Together, in 1 day they produce \((x/y) + \{x/(y+2)\}\) units. So, in 2 days they produce \(2[(x/y) + \{x/(y+2)]\) units = \(x(4y+4)/y(y+2)\) units. According to question, \(\frac{x(4y+4)}{y(y+2)} = \frac{5x}{6}\). \(\Rightarrow 24y + 24 = 5y^2 + 10y \Rightarrow 5y^2 - 14y - 24 = 0\). \(\Rightarrow (5y+6)(y-4)=0\). So \(y=4\) or \(y=-6/5\). Since y can't be negative, so \(y=4\). So, Karim takes \(y+2 = 4+2 = 6\) days to produce x units. So, to produce 3x units, Karim need \(3\times6 = 18\) days.
Related Questions (Any University/Year)
- Ninety-six mangoes are divided among X, Y, and Z in such a way that X received 4 times as many as Z and Z receives 3 times as many as Y. How much did Y receive?
- A helicopter company charges $85 for the first kilometer of a trip and $5 every kilometer after that. If the total cost of a trip was $365, how many kilometers were flown?
- Ratio between two numbers is 2:3 and their sum is 400. The greater of the two number is
- It is 165 miles from Dhaka to Chittagong. If a bus takes 1.5 hours to travel the first 65 miles how long must the bus take to travel the final 100 miles in order average 50 miles for the current trips?
- 3x+y=18, and x+3y=1.Find the value of 2x+2y
- If 7x - 5y = 13 and 2x7y: = 26, then 9x -12y=?
- Instructions: DO NOT USE CALCULATOR. Figures are not drawn to scale. Arif can do a work in 12 hours. Arif finished two-thirds of the work and the remaining portion of the work was done by Babu, whose rate of working is just 20% of what Arif can do. How long did it take Babu to finish the remaining work in hours?
- A man and his wife have seven sons, and every one of the sons has a sister, How many are there in the family?
- Alam starts working on a job and works on work. Then babu joins Alam and together they complete the est of the work in 12 days . How long (in days) will it take Babu to complete the job if he works alone ?
- Terra Data asked a team of workers to finish a project. After 16 days, 25% workers left. Remaining workers took the same number of days to finish rest of the work that the original team would have taken to complete the entire project. In how many days was the entire project finally completed?
- The number of students on each section of a school is 24. After admitting new students, three new sections were started. Now, the total number of sections is 16 and there are 21 students in each section. How many new students were admitted?
- 20% of 50 = 50% of?
- Which of these is NOT a correct way to find 75% of 25?
- If P and Q are positive integers, which CANNOT be the greatest common divisor of P and Q?
- How many squares with sides ---inch long are needed to cover a rectangle that is 4 feet long and 6 feet wide?
- The average mark obtain by 10 students was 6 and the average mark obtained by 6 students was 17. What was the average mark obtained by all 16 students ___.
- A certain machine can make 3 widgets every 27 seconds. At this rate, how many widgets will be made in 1 minute?
- The difference between two positive numbers is 16. If the smaller of those two numbers is 3/5th of the larger, what is the value of the smaller number?
- A straight fence is to be constructed from posts 6 inches wide and separated by lengths of chain 5 feet long. If a certain fence begins and ends with a post, which of the following could be the length of the fence in feet? (12 inches = 1 foot). Indicate ALL such answers.
- A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?