2 men and 5 women completed only 1/4th portion of a job in 3 days. After 3 days another man was included in the team and in 2 days they completed another 1/4th portion of the job. How many men (with no women) can complete the whole job in 4 days?
UIUSUMMERসাধারণ গণিতবীজগণিতীয় রাশিঐকিক নিয়ম (কাজ ও সময়) (Topic Practice)UIU - ⚡ অনলাইন প্রশ্নব্যাংক দেখুন 💥
সঠিক উত্তরঃ
C.
6
Explanation: